Progress Report to April 2013

As completion of Phase 1 dawns on Hope Estate, we are all enthusiastically working overtime to ensure that we make our revised May 2013 deadline for obtaining the Completion Certificate from the Tobago House of Assembly. In doing so, we have dedicated our time and resources in meeting and communicating with all the relevant Governmental Agencies involved so as to ensure that Phase 1 meets all approval standards/standards and the delivery process runs smoothly.

Notwithstanding, we are please to inform you of the progress made on Phase I to date:

  • 95% completion of the sewer lines
  • 80% completion of the water connections to the plots
  • 75% of the electrical, cable and phone lines
  • 70% completion of the sub base of the road network
  • 60% of the drainage network

Simultaneously, the infrastructural work on Phase 2 is well underway with basic earth works 80% complete. In addition, we have already engaged the use of new machinery and have contracted additional work crews in order to meet our development timelines for Phase 2, which will yield the following benefits:

  • 12 lots remaining at pre-construction prices
  • High-end finishes inclusive with underground utilities
  • Security and privacy
  • Convenience of a commercial zone
  • Walking distance to the beach
  • Community oriented living
  • Scenic views

Book your tour and choose your lot today to become part of the Hope Estate lifestyle!

Warm Regards

The Hope Estate Management Team