Progress Report to February 2013

We present below the progress reports for Phase I and Phase II of Hope Estate:

Phase I progress

We are pleased to inform you of the progress made on Phase I to date:

  • 95% completion of the sewer lines
  • 80% completion of the water connections to the plots
  • 75% of the electrical, cable and phone lines
  • 65% completion of the sub base* of the road network
  • 30% of the drainage network
laying electrical lines on road H

Laying the electrical lines on Road H

*The sub base is the layer of the road which is comprised of rotten rock. It rests below the base which is comprised of crusher run and the pitch which is the last layer of the road.

As Phase I’s completion date of May 2013 draws closer, we will coordinate the construction effort with the needed approvals to ensure a smooth delivery of deeds to you




Phase II

To date, 80% of the basic road works has already been completed.

We remind you of the great features that wil also be a part of Phase II

  • High end finish with underground utilities
  • Security and privacy
  • Convenience of commercial strip
  • Walking distance to the beach
  • Community oriented living.

Also, there are 12 plots in Phase II which are still available at pre-construction prices.
Book a tour and choose your plot today and become a part of the Hope Estate Lifestyle.

Warm Regards
The Hope Estate Management Team